Separate Contracts, Separate Forums: Arbitration Clauses in Multi-Agreement Relationships
Listen to Article
Prabhat VoiceListen to natural Indian English narration

The Supreme Court of India, in Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors., examined a recurring problem in commercial arbitration. If parties sign several related agreements, each with its own arbitration clause, can the dispute resolution clause of one “mother agreement” override the others? The Court answered in the negative where the agreements prima facie operate in different fields and the disputes arise exclusively under the later agreements. The judgment also reaffirms that a Section 11 court must confine itself to the prima facie existence of an arbitration agreement and leave contested questions, such as the binding of non-signatories, to the arbitrator.
Facts of the Case
The dispute involved an Indian company, Shubham Equipment Private Limited (SEPL), and a South Korean patent-holding company, Rothwell Water Company Limited (RWCL). Their relationship rested on three agreements. The first was a Technical Collaboration Licence Agreement dated 30 January 2019, under which RWCL granted SEPL an exclusive, royalty-bearing licence for certain wastewater treatment patents. Clause 12.1 provided for arbitration in Seoul under Korean law. The second was a Joint Venture Agreement and Share Holding Agreement (JVA) dated 1 October 2021, which created Rothwell Water (India) Private Limited, a joint venture company in India. Article 43 provided for arbitration in Mumbai under Indian law. The third was a Memorandum of Understanding (MoU) dated 1 February 2023, under which SEPL was to provide liaison, customs clearance and logistics services to RWCL on a municipal project. Clause 9 provided for a sole arbitrator, with Mumbai as seat and venue.
On 11 October 2024, SEPL terminated the JVA. It alleged that RWCL had incorporated its wholly owned subsidiary, Rothwell Business International Private Limited (RBIPL), to compete with the joint venture, in breach of the non-compete covenant in Article 24.1. SEPL also alleged that RWCL had delayed technical inputs and then rejected projects on grounds of technical incompetence. It claimed Rs. 20 crore for business loss and Rs. 4.24 crore under the MoU for costs and taxes incurred on RWCL’s behalf.
RWCL contested the claims and said the disputes were linked to the Licence Agreement, so the Seoul arbitration clause should apply. SEPL served arbitration notices on 28 November 2024 and then filed petitions under Section 11 of the Arbitration and Conciliation Act, 1996. RWCL then issued its own arbitration notice in Korea on 8 August 2025, alleging breach of the exclusivity clause in the Licence Agreement. The Court first referred the matter to mediation. Some progress was made, but no settlement was reached, and the Court therefore decided the petitions on merits.
The Main Issue
The central question was whether disputes under the JVA and MoU had to be arbitrated under their own clauses in Mumbai, or whether they were subsumed by Clause 12.1 of the Licence Agreement, which required arbitration in Korea. The respondents did not deny that disputes existed. They argued that the JVA and MoU were intertwined with the Licence Agreement and had no independent existence. They also said the petitioners had not attempted amicable resolution, and that RBIPL, as a non-signatory, could not be bound by any arbitration agreement.
The petitioners argued that the agreements were independent. They relied on Article 25 of the JVA and Clause 10.8 of the MoU, which provide that each agreement is the entire agreement on its subject matter and supersedes earlier ones. They said RBIPL was a necessary party because it was allegedly set up to breach the JVA.
Court’s Analysis
The Court began with the limited role of a referral court. It relied on Section 11(6-A) and, in a footnote, on In re: Interplay Between Arbitration Agreements under the Arbitration and Conciliation Act, 1996 and the Indian Stamp Act, 1899 (2024) 6 SCC 1, which restrict the inquiry to the prima facie existence of an arbitration agreement. This is the only precedent the order cites. Once that is shown, the court should appoint an arbitrator. The existence of the agreements was admitted here.
The Court then compared the three agreements. The Licence Agreement grants patent licences. The JVA creates an Indian joint venture company. The MoU is a services arrangement for a specific project. Because they prima facie operate in different fields, disputes arising exclusively under the JVA and MoU are amenable to the clauses in those agreements, not to Clause 12.1.
The Court said its view was fortified by the entire-agreement provisions. Article 25 of the JVA and Clause 10.8 of the MoU both state that the agreement supersedes prior agreements on its subject matter.
The respondents also argued that the disputes overlap with claims they have already raised in Korea. The Court held that this concerns the scope and ambit of disputes arbitrable under the JVA and MoU, which is for the arbitrator. It is not a ground to refuse reference at the threshold.
On RBIPL, the Court called the non-signatory objection “contentious”. RBIPL is a wholly owned subsidiary of a signatory and is alleged to have been incorporated in derogation of the JVA. The Court left the question to the arbitrator.
Ratio and Significance
Where parties execute several agreements with different subject matter and each has its own arbitration clause, disputes arising exclusively under an agreement go to the forum that agreement prescribes. A related agreement with a different seat does not displace it. At the Section 11 stage, courts should not decide overlap between claims, the exact scope of arbitrable disputes, or whether a non-signatory can be bound. Those questions belong to the tribunal.
The judgment also shows how entire-agreement clauses can support the independence of a contract, since they can indicate that later agreements were meant to stand on their own terms. The Court did not decide whether RBIPL is bound or whether the disputes truly overlap with the Licence Agreement. It decided only that these issues do not stop the appointment of an arbitrator.
Conclusion
The Supreme Court allowed both arbitration petitions and appointed Justice Ramesh Deokinandan Dhanuka, former Chief Justice of the Bombay High Court, as sole arbitrator, with liberty to fix his own fees. There was no order as to costs. The order was authored by Justice Joymalya Bagchi, on a bench with CJI Surya Kant and Justice V. Mohana.
The significance of Shubham Equipment lies in its practical message for commercial parties. Multi-contract relationships often carry inconsistent dispute resolution clauses, and with one arbitration in Mumbai and another invoked in Seoul, the risk of parallel proceedings is real. The judgment shows that courts will not use this inconsistency to deny a reference. Parties who want a single forum should align their clauses when drafting.
Read the full Judgment here: Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors., 2026 INSC 1098
Written by
Baby Fatma
3rd Year Student at faculty of Law, Jamia Millia Islamia, New Delhi, and contributing writer and Research correspondent at FairLex.
Start the Conversation
Share your perspective on this article



